Zero-Downtime Multi-TB Migrations: Cutover, Validation and Rollback (Part 2)

“The plan looks great. So what actually happens at 2am on Sunday?”

That was the CTO again, once we’d walked through Part 1: logical replication, the database split into units, five waves, the last one fixed on Sunday 6. Fair question. A plan is only as good as the night you run it.

So this part is about that night: how we proved the data matched, how a cutover fits into five minutes, how to keep a way back you can actually use, and why we rehearsed until it was dull. Functional testing of the apps is still out of scope. What customers see during the pause, and when a payment gets rolled back, is very much in.

Prove the data matches

We agreed what “matching” meant before we started, because 3am is a bad time for that argument. We checked in three layers, cheapest first:

  1. Row counts per table. They catch the embarrassing stuff, like a table that never started replicating.
  2. Checksums by primary key range. A mismatch points at one chunk instead of 3 TB. Frozen ranges you can compare any time. Hot tables need a fixed snapshot, because a live comparison reports lag as corruption. And please don’t hash 3 TB on the primary in the middle of the business day.
  3. Business checks. Yesterday’s payment total, merchant balances, the highest order ID. Whatever finance will check on Monday, check it first.

Collation deserves its own warning. Compare by key, not by sorted text, because a newer glibc or ICU can put the same rows in a different order, and that’s just a false alarm. A unique text index that won’t build, or that treats two values differently, is a real failure, and we treated it as one.

We validated continuously during catch up, unit by unit. And since this was an upgrade as well, we ran ANALYZE after each copy and compared the plans of the busiest queries on both sides. Not load testing, just making sure 16 hadn’t picked a very different route.

Rehearse at full size

You can’t copy 12 TB five times inside a twelve week lease, so we didn’t try. We did two full size rehearsals against real replication, a second subscription off production into a scratch instance, with real lag and the real roles, and used smaller copies to drill the SQL. A 50 GB sample would never have shown us the WAL pressure, the apply lag or the CTE regression.

We ran each one like the real night and timed every step. And we proved the way back: a PostgreSQL 11 database subscribed to 16, applying a real peak hour. If you skip one rehearsal, don’t let it be that one.

Here’s some of what the rehearsals turned up:

Every one of those would have been a bad night in production. In rehearsal, they were just tickets.

Cut over one wave at a time

Every cutover follows the same idea. Everything that’s moving has been replicating old to new since day one, one publication per unit. A cutover just flips one unit: its tables stop being written on the old side and copied across, and start being written on the new side and copied back. At any moment each table has exactly one writing side, and both databases hold all the live data.

The runbook was short, and every step had a named owner (shown by role in the card below).

An hour before, we ran the go or no go. Every answer had to be yes:

One no, and we used a spare Sunday. That’s what they’re for.

Then the clock started. These are wave 1’s times from its final rehearsal:

1
2
3
4
5
6
buffer
0:001:002:003:004:005:00
0:00
1
Stop writes for this unitDBA
Revoke insert, update and delete from every role that writes these tables, the owner too if the app connects as it. Then cancel only the sessions holding locks on them. Reads and the other waves carry on. Any transaction still in flight rolls back and the app retries, which for payments is a business event, so agree up front what customers see. Note the WAL position on the old side.
0:20
2
Wait for lag to hit zeroDBA
Other waves are still writing, so the old side's WAL never stops moving. Ignore that. Watch this unit's slot on the old side instead: its confirmed_flush_lsn in pg_replication_slots shows how far the new side has applied. Wait until it reaches the step 1 position. Not close. All of it.
1:10
3
Quick final checkDBA
Row counts and checksums on the newest chunks only. Writes are stopped, so this is a stable point to compare.
1:50
4
Set the sequencesDBA
Read each sequence's last_value on the old side and set the new side above it, with a gap. Not max(id): too slow on 3.1 billion rows, and it can be lower than what's already been handed out.
2:05
5
Flip the replicationDBA
Disable the old to new subscription and drop its slot, or it holds WAL until the disk fills. That's the only loop protection 11 gives you. Then create the slot on the new side, enable the staged reverse subscription, and refresh it without copying data.
2:25
6
Point the services at the new sideApp lead
Apply the write grants on the new side, switch the connection strings and restart the pools. If you switch by DNS, lower the TTL days ahead. Anything still pointing at the old side hits the revoked grants and fails loudly. The pause ends here.
2:50
Writes are flowing on the new side. Everything after this is two minutes of buffer you hope not to need.

The first time we rehearsed wave 1 it took eleven minutes. On the night it was under three, mostly because steps 2 to 5 were scripted and nobody was typing SQL under pressure.

Run two databases at once

For a few weeks you’re running two databases, with replication flowing both ways, and it feels odd. These were the rules that kept it safe:

Keep a way back

How you roll back depends on where you are in the runbook when something goes wrong. We planned for three cases:

Before step 5
Just go home
Nothing has changed on the new side. Grant writes back on the old side and point the services home.
Costs: one spare Sunday
After step 5, before any new write
Rebuild the forward stream
The forward slot is gone. Disable the reverse subscription and drop its slot, recreate old to new without copying data, then grant and point home.
Costs: the rest of the night. Wait a week and it's a fresh copy
After the new side takes writes
Run the cutover backwards
Only works if 11 can keep up with 16. Stop writes on the new side, let the old side catch up, set its sequences, flip the replication, grant writes back, point home.
Costs: the same five minutes, if rehearsal proved it

The first two are mostly about keeping your nerve. We used the first one once, in a rehearsal, when the lag check stalled at 1:40 and nobody wanted to guess why. The apps were back on the old side a couple of minutes later.

The third case took the most work. Going from 16 back to 11 means replicating down five major versions, and PostgreSQL doesn’t promise that works, so we tested it: an 11 database subscribed to 16 through a full peak hour in rehearsal. It held. If it hadn’t, we’d have told the CTO plainly that once the new side takes its first write there’s no clean way back, and then either lived with that or built a separate feed of changes that 11 could replay. And don’t forget to grant writes back on the old side. We nearly did, in rehearsal, and the apps came home to a database that wouldn’t let them write.

If you ever have to undo more than one wave, go in reverse order, one unit at a time, or a payment can end up pointing at a category the old side hasn’t got yet.

We kept the old database running, patched and monitored for two weeks after the last wave, or until the first schema change on the new side, whichever came first. That was our point of no return, and it’s why Sunday 6 had to be the last cutover. Finance asked twice whether we really needed to keep paying for it. We did.

What bites people

If I had to name the ones I see most often:

None of these are exotic. They’re just what gets skipped under deadline pressure, which is always.

Several of them you can catch on day one, before a single subscription exists. I’ve put the read-only check we wish we’d run first into a script: pg-logical-replication-precheck.sql. Point it at the source with psql -X -f. It lists tables without a primary key, sequences and their current values, partitions, large objects, triggers that would fire twice, extensions, MD5 passwords, risky unique text indexes, and any replication slot already quietly holding WAL. It doesn’t write or lock anything, and it won’t find the cron job on the old VM. That still takes a month of connection logs.

Wrapping up

So how did it go? Mostly to plan. One wave slipped a week after a validation false alarm (the check had compared a live chunk while the subscriber was a second behind), and that’s exactly what the spare Sunday was for. All five cutovers finished inside four minutes, and the old database was switched off before the lease ran out.

Looking back, nothing we used was new. Logical replication has been in PostgreSQL since version 10, moving in waves is old project management, and the runbook was a checklist on one page. What got us through was doing the dull parts properly: a month of connection logging, rehearsing until the times stopped changing, and keeping a spare Sunday that nobody wanted to give up. The upgrade came along inside the same project instead of becoming a second one. At this size, the plan matters far more than the tool.

References

  1. Logical Replication, PostgreSQL 16 documentation
  2. CREATE SUBSCRIPTION, PostgreSQL 16 documentation, including the copy_data option used when starting reverse replication
  3. Logical Replication Restrictions, PostgreSQL 16 documentation
  4. Monitoring Logical Replication, PostgreSQL 16 documentation
  5. Sequence Manipulation Functions, PostgreSQL 16 documentation
  6. pg_replication_slots, PostgreSQL 16 documentation, for confirmed_flush_lsn and restart_lsn
  7. pg_subscription_rel, PostgreSQL 16 documentation, for per table sync state
  8. PostgreSQL 17 Release Notes, including failover of logical replication slots

Share this post on:

Previous Post
Troubleshooting Data Dictionary Issues in MySQL and Aurora
Next Post
Zero-Downtime Multi-TB Migrations: Strategy and Grouping (Part 1)